Programme de dev de l'année 2026


gantt
    title Programme NCA dev 2026
    dateFormat  DD-MM-YYYY

    section {App CQ}
    PROD {AppCQ}                   :01-03-2026, 05-05-2026
    [1ere phase de dev]     :01-03-2026, 08-04-2026
    [CQ & retour Yves]      :01-04-2026, 24-04-2026
    [Dev finaux]            :24-04-2026, 05-05-2026
    Milestone               :milestone, 05-05-2026, 0d

    section {App GenEst}
    PROD {GenEst}                   :24-04-2026, 31-05-2026
    DEV1 - Token                    :23-03-2026, 1.5w
    DEV2 - Rapports auto            :24-04-2026, 2w
    DEV3 - Graphiques               :18-05-2026, 1.5w
    Milestone                       :milestone, 31-05-2026, 0d

    section {ProtectChiro}
    PROD {ProtectChiro}             :18-05-2026, 01-07-2026
    DEV1 - Système d'import         :pcd1, 18-05-2026, 15d
    DEV2 - Multiple years           :pcd2, after pcd1, 12d
    DEV3 - Finalisation             :after pcd2, 15d
    Milestone                       :milestone, 01-07-2026, 0d

    section {Collision} 
    PROD {Collision}                :01-07-2026, 31-08-2026
    DEV1 - Token                    :cd1, 01-07-2026, 1w
    DEV2 - Rapports auto            :cd2, after cd1, 2w
    DEV3 - Export DEPOTBIO          :cd3, after cd2, 2w
    DEV4 - RefMorta brutes          :cd4, after cd3, 2w
    DEV5 - Finalisation             :after cd4, 2w
    Milestone                       :milestone, 01-09-2026, 0d

    section {ActiChiro}
    PROD {Actichrio}                :01-07-2026, 31-08-2026
    A definir                       :01-07-2026, 2w
    Milestone                       :milestone, 01-09-2026, 0d

    section Vacances
    Ecosse              : 10-04-2026, 24-04-2026
    Normandie           : 06-05-2026, 18-05-2026